  • Exterior end piece panel installation
  • Dock lift installation
  • Priming and painting interior
  • ACT ceiling grid and tile both levels
  • Millwork installation
  • Stair 1 railings
  • Circular soffit light fixtures
  • Elevator installation
  • MEP trim in ceiling on lower level
  • Doors and hardware in gun range