by Mission94 | Mar 28, 2024 | Construction Updates
Mission94 construction update as of March 28, 2024: Punch list Final cleaning As construction is completed, the team is looking forward to welcoming guests at the Grand Opening in July. VIEW ALL CONSTRUCTION...
by Mission94 | Mar 21, 2024 | Construction Updates
Mission94 construction update as of March 21, 2024: Plumbing, elevator, building HVAC, building inspections Fire department final walk through Flooring and base Millwork Retail and office furniture Pre-punch and punch list Final cleaning Lower level curved wall panels...
by Mission94 | Mar 14, 2024 | Construction Updates
Mission94 construction update as of March 14, 2024: Sprinkler, solar, fire alarm, exterior/landscaping inspections Fire alarm testing Polish concrete floors Restroom plumbing trim and accessories Flooring and base Millwork Retail Furniture Doors and hardware Dock area...
by Mission94 | Mar 7, 2024 | Construction Updates
Mission94 construction update as of March 7, 2024: Polish concrete floors Restroom plumbing trim, counter tops, and accessories Flooring and base Millwork Doors and hardware Fire alarm testing and inspection Lower level window installation Gun range equipment and...
by Mission94 | Feb 29, 2024 | Construction Updates
Mission94 construction update as of February 29, 2024: Dock lift installation Exterior end piece panel ACT ceiling grid and tile Light fixtures in all areas Polish concrete floors Restroom plumbing trim, counter tops, accessories Stair 1 railings and tile Paint...